The client
Brand Standard Furnishings (BSF) delivers furniture for hotel projects, from the factory order to the last room installed. Its project managers keep several hotel projects moving at once, each with its own factories, shipments and installation crews.
The challenge
The factory puts its ship date on the order confirmation. The hotel puts the crew’s start date on the installation plan. Read either document on its own and nothing tells the project manager the two dates conflict.
So managers rechecked orders floor by floor to find the items that could hold up an installation. That time went to checking instead of to running more projects.
The approach
We worked with BSF’s project managers on the four checks they repeat on every project: revised drawings, factory confirmations, ship dates against the installation plan, and claims for damaged or missing items. YP prepares each check; the manager decides what to do.
The solution
YP connects the documents that used to live apart: the drawing, the purchase order, the factory’s confirmation, the shipping notice and the hotel’s installation plan.
From factory order to installed room
Revised drawings checked against the designer’s comments.
Every new drawing revision is compared with the designer’s comments, so nothing goes to production on an old version.
Use case: Shop drawings checked against the specFactory confirmations checked against the order.
YP checks each confirmation against the purchase order: item, finish, quantity and ship date.
Use case: Order acknowledgments checked line by lineShip dates matched to the installation plan.
When a ship date clashes with the crew’s start date, the manager sees the floor and room type affected, with a question to review before calling the supplier. The manager can ask for a split shipment or move the crew to another floor.
Use case: Ship dates checked against the install planClaims prepared for damaged or missing items.
Items damaged or missing at installation become draft claims and replacement orders, with the deadline for each claim.
Use case: Punch list items to replacement orders
The results
BSF’s project managers save 10 hours per project each week, and each manager can oversee more active hotel projects. A manager can call the factory about a late shipment without rechecking every order due on that floor.